[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128321,793,1,"单选题","如果澄清和修改通知发出的时间距投标截止时间不足（? ）天，且影响投标文件编制的，相应延长投标截止时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20天",false,{"key":16,"text":17,"correct":18},"B","15天",true,{"key":20,"text":21,"correct":14},"C","25天",{"key":23,"text":24,"correct":14},"D","30天","2020版教材P184 如果澄清和修改通知发出的时间距投标截止时间不足15天，且影响投标文件编制的，相应延长投标截止时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]