[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1128317,793,1,"单选题","某次水利工程施工招标中，只有甲、乙两家投标单位递交了投标文件，根据水利工程招标投标有关规定，招标人应当( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直接委托给投标人甲或乙",false,{"key":16,"text":17,"correct":14},"B","组织议标，然后在甲、乙中确定中标人",{"key":19,"text":20,"correct":14},"C","组织评标，然后在甲、乙中确定中标人",{"key":22,"text":23,"correct":24},"D","依法重新招标",true,"2020版教材P185 8.重新招标有下列情形之一的，招标人将重新招标：(1)投标截止时间止，投标人少于3个的；(2)经评标委员会评审后否决所有投标的；(3)评标委员会否决不合格投标或者界定为废标后因有效投标不足3个使得投标明显缺乏竞争，评标委员会决定否决全部投标的；(4)同意延长投标有效期的投标人少于3个的；",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]