[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128310,793,1,"单选题","招标投标阶段的土方回填的工程量的计量应是设计图示尺寸的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压实方体积",false,{"key":16,"text":17,"correct":18},"B","有效压实方体积",true,{"key":20,"text":21,"correct":14},"C","有效自然方体积",{"key":23,"text":24,"correct":14},"D","自然方体积","2020版教材P177 (2) 坝 （ 堤）体全部完成后，最终结算的工程量应是经过施工期间压实并经自然沉陷 后按施工图纸所示尺寸计算的有效压实方体积。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]