[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128309":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1128309,793,1,"单选题","根据《水利工程设计概估算制规定(工程部分）》（水总[2014]429号文），水利工程费用中，直接费不包括（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工机械使用费",false,{"key":16,"text":17,"correct":14},"B","临时设施费",{"key":19,"text":20,"correct":14},"C","安全生产措施费",{"key":22,"text":23,"correct":24},"D","现场经费",true,"2020版教材P162 “直接费由基本直接费、其他直接费组成。基本直接费包括人工费、材料费、施工机械使用费。其他直接费包括冬雨期施工增加费、夜间施工增加费、特殊地区施工增加费、临时设施费、安全生产措施费和其他。”",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]