[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128298,793,1,"单选题","某水利建筑工程的机电设备安装工程的单价计算中，直接费为Ⅰ，基本直接费为Ⅱ，人工费为Ⅲ，机械使用费其为Ⅳ，他直接费为Ⅴ，已知间接费的费率为η，则间接费为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅰ×η",true,{"key":16,"text":17,"correct":18},"B","Ⅱ×η",false,{"key":20,"text":21,"correct":18},"C","Ⅲ×η",{"key":23,"text":24,"correct":18},"D","(Ⅰ+Ⅳ+Ⅴ)×η","2020版教材P166 间接费：直接费×间接费率.",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]