[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128297,793,1,"单选题","某水利工程人工预算单价中级工5元／工时，柴油3.2元／kg，台时一类费用调整系数1.0（已知定额查得第一类费用：42.67元／台时；第二类费用：2.4工时／台时，柴油10.6kg台时），则该74kW推土机的台时费为( )元／台时。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","42.67",false,{"key":16,"text":17,"correct":14},"B","45.92",{"key":19,"text":20,"correct":21},"C","88.59",true,{"key":23,"text":24,"correct":14},"D","109.65","2020版教材P165 施工机械使用费是计算建筑安装工程单价中机械使用费的基础，指一台施工机械正常工作一小时所支出和分摊的各项费用之和，由第一类和第二类费用组成。第一类费用由折旧费，修理费，替换设备费，安装拆卸费组成。第二类费用指施工机械正常运转时机上人工及动力、燃料消耗费。5×2.4+3.2×10.6+42.67=88.59元\u002F台时。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]