[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128293,793,1,"单选题","招投标阶段，砌筑工程的工程量计算下列说法正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","砌筑工程的砂浆费用，包含在《工程量清单》相应砌筑项目有效工程量的每立方米工程单价中，不另行支付",true,{"key":16,"text":17,"correct":18},"B","干砌石的费用包括在相应项目有效工程量的每立方米工程单价中，不另行支付",false,{"key":20,"text":21,"correct":18},"C","砌筑工程的拉结筋费用需要另行支付",{"key":23,"text":24,"correct":18},"D","砌筑工程的砂浆费用不包含在《工程量清单》相应砌筑项目有效工程量的每立方米工程单价中","2020版教材P179 (1)浆砌石、干砌石、混凝土预制块和砖砌体按施工图纸所图尺寸计算的有效砌筑体积以立方米为单位计量，按《工程量清单》相应项目有效工程量的每立方米工程量单价支付。(2)砌筑工程的砂浆、拉结筋、垫层、排水管、止水设施、伸缩缝、沉降缝及埋设件等费用，包含在《工程量清单》相应砌筑项目有效工程量的每立方米工程单价中，不另行支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]