[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128292,793,1,"单选题","招投标阶段，混凝土工程单价不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以总价支付的混凝土配合比费用",true,{"key":16,"text":17,"correct":18},"B","由于超挖引起的超填量的费用",false,{"key":20,"text":21,"correct":18},"C","温控措施费",{"key":23,"text":24,"correct":18},"D","冬期施工增加费","2020版教材P178 (5)施工过程中，承包人进行的各项混凝土试验所需的费用（不包括以总价形式支付的混凝土配合比试验费），均包含在《工程量清单》相应项目有效工程量的每立方米工程单价中，不另行支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]