[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128290":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128290,793,1,"单选题","坝（堤）体全部完成后，土石方填筑工程量应按( )计算填筑体的有效压实方体积计量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工期间压实并经自然沉陷后按施工图纸所示尺寸计算的有效压实方体积",true,{"key":16,"text":17,"correct":18},"B","招投标设计图示尺寸加超挖量",false,{"key":20,"text":21,"correct":18},"C","招投标设计图示尺寸加施工附加量",{"key":23,"text":24,"correct":18},"D","招投标设计图示尺寸加沉陷损失","2020版教材P177 (2)坝（堤）体全部完成后，最终结算的工程量应是经过施工期间压实并经自然沉陷后按施工图纸所示尺寸计算的有效压实方体积。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]