[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128288,793,1,"单选题","招标投标阶段的混凝土工程量计量时，不予扣除的空洞截面面积是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","小于0.1㎡",true,{"key":16,"text":17,"correct":18},"B","小于0.2㎡",false,{"key":20,"text":21,"correct":18},"C","小于0.3㎡",{"key":23,"text":24,"correct":18},"D","小于0.4㎡","2020版教材P178 (2) 混凝土有效工程量不扣除设计单体体积小于0.1m3 的圆角或斜角，单体占用的空间体积小于0.1m3 的钢筋和金属件，单体横截面积小于0.1m2 的孔洞、排水管、预埋管和凹槽等所占的体积，按设计要求对上述孔洞回填的混凝土也不予计量",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]