[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1128280,793,1,"单选题","挖掘机、轮斗挖掘机或装载机挖装土（含渠道土方）自卸汽车运输定额，适用于Ⅲ类土。Ⅰ、Ⅱ类土人工、机械调整系数均取( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.61",false,{"key":16,"text":17,"correct":14},"B","0.71",{"key":19,"text":20,"correct":14},"C","0.81",{"key":22,"text":23,"correct":24},"D","0.91",true,"2020版教材P170 (5)挖掘机、轮斗挖掘机或装载机挖装土（含渠道土方）自卸汽车运输定额，适用于ID类土。I、II类土人工、机械调整系数均取0.91，IV类土人工、机械调整系数均取1.09。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]