[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128267,793,1,"单选题","编制施工总进度时，工程施工总工期不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程筹建期",true,{"key":16,"text":17,"correct":18},"B","工程准备期",false,{"key":20,"text":21,"correct":18},"C","主体工程施工期",{"key":23,"text":24,"correct":18},"D","工程完建期","2020版教材P156 工程建设全过程可划分为工程筹建期、工程准备期、主体工程施工期和工程完建期四个施工时段。编制施工总进度时，工程施工总工期应为后三项工期之和。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]