[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128264,793,1,"单选题","下列关于水利水电工程进度曲线的绘制说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以时间为横轴，以完成累计完成工作量为纵轴",true,{"key":16,"text":17,"correct":18},"B","以时间为横轴，以单位时间内完成工作量为纵轴",false,{"key":20,"text":21,"correct":18},"C","以完成累计工作量为横轴，以时间为纵轴",{"key":23,"text":24,"correct":18},"D","以单位时间内完成工作量为横轴，以时间为纵轴","2020版教材P157 工程进度曲线是以时间为横轴、以完成累计工作量为纵轴，按计划时间累计完成任务量的曲线作为预定的进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]