[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128262,793,1,"单选题","下列关于施工总布置的说法错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对于大规模水利水电工程，应在主体工程施工前征用所有永久和临时占地，以方便统筹考虑临时设施的布置",true,{"key":16,"text":17,"correct":18},"B","临时设施最好不占用拟建永久性建筑物和设施的位置，以避免不必要的损失和浪费",false,{"key":20,"text":21,"correct":18},"C","为了降低临时工程的费用，应尽最大可能利用现有的建筑物以及可供施工使用的设施",{"key":23,"text":24,"correct":18},"D","储存燃料及易燃物品的仓库距拟建工程及其他临时性建筑物不得小于50m","2020版教材P151 （1）在保证施工顺利的前提下，尽量少占耕地。在进行大规模水利水电工程施工时，要根据各阶段施工平面图的要求，分期分批地征用土地，以便做到少占耕地或缩短占用土地时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]