[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128261,793,1,"单选题","水利水电工程施工中，汛期的防洪、泄洪设施的用电负荷属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一类负荷",true,{"key":16,"text":17,"correct":18},"B","二类负荷",false,{"key":20,"text":21,"correct":18},"C","三类负荷",{"key":23,"text":24,"correct":18},"D","四类负荷","2020版教材P155 水利水电工程施工现场一类负荷主要有井、洞内照明、排水、通风和基坑内排水、汛期的防洪、泄洪设施以及医院的手术室、急诊室、重要的通信站以及其他因停电即可能造成人身伤亡或设备事故引起国家财产严重损失的重要负荷。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]