[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128257,793,1,"单选题","下列关于施工进度计划横道图的说法错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","能表示出各项工作的划分、工作的开始时间和完成时间及工作之间的相互搭接关系",false,{"key":16,"text":17,"correct":18},"B","能反映工程费用与工期之间的关系，因而便于缩短工期和降低成本",true,{"key":20,"text":21,"correct":14},"C","不能明确反映出各项工作之间错综复杂的相互关系，不利于建设工程进度的动态控制",{"key":23,"text":24,"correct":14},"D","不能明确地反映出影响工期的关键工作和关键线路，不便于进度控制人员抓住主要矛盾","2020版教材P157 利用施工横道图表示工程进度计划，存在下列缺点,（4）不能反映工程费用与工期之间的关系，不便于缩短工期和降低成本。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]