[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128250,793,1,"单选题","水利建设项目( )是在项目竣工验收且投入使用后，或未进行竣工验收但主体工程已建成投产多年后，对照项目立项及建设相关文件资料，与项目建成后所达到的实际效果进行对比分析，总结经验教训，提出对策建议。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设实施阶段",false,{"key":16,"text":17,"correct":14},"B","竣工验收阶段",{"key":19,"text":20,"correct":21},"C","后评价",true,{"key":23,"text":24,"correct":14},"D","施工准备阶段","2020版教材P133 水利建设项目后评价是水利建设投资管理程序的重要环节，是在项目竣工验收且投入使用后，或未进行竣工验收但主体工程已建成投产多年后，对照项目立项及建设相关文件资料，与项目建成后所达到的实际效果进行对比分析，总结经验教训，提出对策建议。也可针对项目的某一问题进行专题评价。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]