[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128226,793,1,"单选题","施工图设计过程中，如涉及重大设计变更问题应采取的做法是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由设计单位决定",false,{"key":16,"text":17,"correct":18},"B","报原初步设计批准机关审定",true,{"key":20,"text":21,"correct":14},"C","报主管部门决定",{"key":23,"text":24,"correct":14},"D","由项目法人决定","2020版教材P142 施工详图经监理单位审核后交施工单位施工。设计单位对不涉及重大设计原则问题的合理意见应当采纳并修改设计。若有分歧意见，由项目法人决定。如涉及重大设计变更问题，应当由原初步设计批准部门审定。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]