[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128220,793,1,"单选题","建设项目管理“三项”制度中，对招标的实施最具推动作用的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目法人责任制",false,{"key":16,"text":17,"correct":18},"B","招标投标制",true,{"key":20,"text":21,"correct":14},"C","建设监理制",{"key":23,"text":24,"correct":14},"D","合同管理制","2020版教材P134 水利部20世纪80年代曾颁发《水利工程施工招标投标工作管理规定》，1995年颁发《水利工程建设项目施工招标投标管理规定》，1998年对此规定进行修改后重新发布，该规定对于水利工程建设项目的招标投标工作起了重要的推进作用。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]