[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128114,793,1,"单选题","关于钢筋的剪切，说法错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","钢筋切断应 根据配料表中编号、直径、长度和数量，长短搭配",false,{"key":16,"text":17,"correct":14},"B","同直径、同钢号且不同长度的各种钢筋编号( 设计编号)应先按顺序编制配料表",{"key":19,"text":20,"correct":21},"C","应根据调直前的钢筋长度和混凝土结构对钢筋接头的要求，统一配料",true,{"key":23,"text":24,"correct":14},"D","下料长度应根据结构尺寸、混凝土保护层厚度、钢筋弯曲调整值和弯钩增加长度 等要求确定","2021\u002F2020版教材P99 3.钢筋下料剪切 钢筋下料长度应根据结构尺寸、混凝土保护层厚度、钢筋弯曲调整值和弯钩增加长度 等要求确定。同直径、同钢号且不同长度的各种钢筋编号( 设计编号)应先按顺序编制配 料表，再根据调直后的钢筋长度和混凝土结构对钢筋接头的要求，统一配料。 钢筋切断应 根据配料表中编号、直径、长度和数量，长短搭配。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]