[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128096,793,1,"单选题","土石坝采用进退错距法施工，若施工工作面宽3.0m，碾压机械碾滚净宽1.5m，设计碾压遍数为5遍，则错距碾压宽度为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.3",true,{"key":16,"text":17,"correct":18},"B","0.5",false,{"key":20,"text":21,"correct":18},"C","0.6",{"key":23,"text":24,"correct":18},"D","2.0","2021\u002F2020版教材P88页 2F313032计算式b=B\u002Fn B-碾滚净宽，n-设计碾压遍数b=1.5\u002F5=0.3。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]