[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128072,793,1,"单选题","防渗墙墙体质量检查应在成墙（）d后进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","35","2021\u002F2020版教材P85 墙体质量检查应在成墙28d后进行，检查内容为必要的墙体物理力学性能指标、墙段 接缝和可能存在的缺陷。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]