[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127907,793,1,"单选题","根据《水利工程建设项目档案管理规定》（水办[2005]480号），进行档案验收时，对档案的抽检数量不得少于应保存档案数量的（ ）%。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","8",true,{"key":23,"text":24,"correct":14},"D","10","本题考查的是水利工程专项验收的要求。根据水利工程建设规模，抽査各单位档案整理情况。抽查比例一般不得少于项目法人应保存档案数量的8% ，其中竣工图不得少于一套竣工图总张数的10%； 抽查档案总量应在200卷以上。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]