[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127906":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127906,793,1,"单选题","竣工验收应在工程建设项目全部完成并满足一定运行条件后（ ）年内进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","1",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","2","本题考查的是水利工程竣工验收的要求。竣工验收应在工程建设项目全部完成并满足一定运行条件后1年内进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]