[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127901,793,1,"单选题","根据《水利水电建设工程验收规程》（SL223--2008），水库蓄水验收属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","阶段验收",true,{"key":16,"text":17,"correct":18},"B","初步验收",false,{"key":20,"text":21,"correct":18},"C","完工验收",{"key":23,"text":24,"correct":18},"D","竣工验收","本题考查的是水利工程阶段验收的要求。根据工程建设要求，当工程建设达到一定关键阶段时（如截流、水库蓄水、机组启动、输水工程通水等），应进行阶段验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]