[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127898,793,1,"单选题","当水利工程施工图图面变更超过（ ）时，施工单位应重新绘制竣工图。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1\u002F5",false,{"key":16,"text":17,"correct":14},"B","1\u002F4",{"key":19,"text":20,"correct":21},"C","1\u002F3",true,{"key":23,"text":24,"correct":14},"D","1\u002F2","本题考查的是水利工程专项验收的要求。凡涉及结构形式、工艺、平面布置等重大改变，或图面变更超过1\u002F3的，应重新绘制竣工图（可不再加盖竣工图章）。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]