[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127896,793,1,"单选题","根据《水电工程验收管理力法》(国能新能[2015]426 号)，枢纽工程专项验收的申请，应由项目法人在计划前（ ）向工程所在地省级人民政府能源主管部门报送。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1个月",false,{"key":16,"text":17,"correct":18},"B","3个月",true,{"key":20,"text":21,"correct":14},"C","6个月",{"key":23,"text":24,"correct":14},"D","12个月","项目法人应根据工程进度安排，在枢纽工程专项验收计划前3个月，向工程所在地省级人民政府能源主管部门报送枢纽工程专项验收申请， 并抄送验收主持单位。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]