[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127865,793,1,"单选题","承包人应在知道或应当知道索赔事件发生后（ ）天内，向监理人递交索赔意向通知书，并说明发生索赔事件的事由。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","56","本题考查的是变更和索赔的处理方法与原则。承包人应在知道或应当知道索赔事件发生后28天内，向监理人递交索赔意向通知书，并说明发生索赔事件的事由。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]