[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127863,793,1,"单选题","根据《水利建设工程施工分包管理规定》（水建管[2005]304号），不得进行工程分包的结构物是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要建筑物的主体结构",true,{"key":16,"text":17,"correct":18},"B","次要建筑物的主体结构",false,{"key":20,"text":21,"correct":18},"C","主要建筑物的全部结构",{"key":23,"text":24,"correct":18},"D","次要建筑物的全部结构","本题考查的是施工分包的要求。水利建设工程的主要建筑物的主体结构不得进行工程分包。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]