[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127859,793,1,"单选题","根据《水利建筑工程预算定额》（2002版），零星材料费以（ ）作为计费基数。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要材料费之和",false,{"key":16,"text":17,"correct":18},"B","人工费机械费之和",true,{"key":20,"text":21,"correct":14},"C","主要机械费之和",{"key":23,"text":24,"correct":14},"D","主要人工费之和","本题考查的是造价编制依据。零星材料费，以人工费机械费之和为计算基数。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]