[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127857,793,1,"单选题","钻孔灌注桩或者沉管灌注桩按施工图纸所示尺寸计算的桩体（ ）为单位计量，按《工程量清单》相应项目有效工程量的每立方米工程单价支付。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际桩长以米",false,{"key":16,"text":17,"correct":18},"B","有效体积以立方米",true,{"key":20,"text":21,"correct":14},"C","有效桩长以米",{"key":23,"text":24,"correct":14},"D","设计体积以立方米","本题考查的是施工阶段计量与支付。钻孔灌注桩或者沉管灌注桩按施工图纸所示尺寸计算的桩体有效体积以立方米为单位计量，按《工程量清单》相应项目有效工程量的每立方米工程单价支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]