[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127854,793,1,"单选题","为完成工程项目施工，发生于该工程项目施工前和施工过程中招标人不要求列明工程量的项目称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目",true,{"key":16,"text":17,"correct":18},"B","其他项目",false,{"key":20,"text":21,"correct":18},"C","零星工作项目",{"key":23,"text":24,"correct":18},"D","分类分项工程项目","本题考查的是投标阶段成本管理。措施项目指为完成工程项目施工，发生于该工程项目施工前和施工过程中招标人不要求列明工程量的项目。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]