[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127851,793,1,"单选题","通过编制工程进度曲线，可获取的信息不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程量完成情况",false,{"key":16,"text":17,"correct":14},"B","实际工程进展速度",{"key":19,"text":20,"correct":21},"C","关键工作",true,{"key":23,"text":24,"correct":14},"D","进度超前或拖延的时间","本题考查的是施工总进度的要求。除了ABD三个选项，还可以获得的信息是后续工程进度预测。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]