[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127850,793,1,"单选题","下列属于水利水电工程施工现场一类负荷的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基坑内的排水施工",true,{"key":16,"text":17,"correct":18},"B","混凝土浇筑施工",false,{"key":20,"text":21,"correct":18},"C","金属结构及机电安装",{"key":23,"text":24,"correct":18},"D","钢筋加工厂","本题考查的是临时设施的要求。水利水电工程施工现场一类负荷主要有井、洞内的照明、排水、通风和基坑内的排水、汛期的防洪、泄洪设施以及医院的手术室、急诊室、重要的通信站以及其他因停电即可能造成人身伤亡或设备事故引起国家财产严重损失的重要负荷。由于单一电源无法确保连续供电，供电可靠性差，因此大中型工程应具有两个以上的电源，否则应建自备电厂。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]