[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127848,793,1,"单选题","低温季节混凝土施工时，提高混凝土拌合料温度不应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","热水拌合",false,{"key":16,"text":17,"correct":14},"B","碎石预热",{"key":19,"text":20,"correct":21},"C","直接加热水泥",true,{"key":23,"text":24,"correct":14},"D","黄沙预热","本题考查的是临时设施的要求。低温季节混凝土施工时，提高混凝土拌合料温度宜用热水拌合机进行骨料预热，水泥不应直接加热。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]