[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127842,793,1,"单选题","建设项目在主体工程开工之前，必须完成各项施工准备工作，其主要工作内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织主体工程施工招标的准备工作",false,{"key":16,"text":17,"correct":14},"B","开展征地:拆迁",{"key":19,"text":20,"correct":21},"C","完成施工图设计",true,{"key":23,"text":24,"correct":14},"D","组织相关监理招标","本题考查的是水利工程施工准备阶段的工作内容。选项C不属于主体工程开工前必须完成的准备工作。施工准备阶段的主要工作有：（1）开展征地、拆迁，实施施工用水、用电、通信、进场道路和场地平整等工程；（2）实施必需的生产、生活临时建筑工程；（3）实施经批准的应急工程、试验工程等专项工程；（4）组织招标设计、咨询、设备和物资采购等服务；（5）组织相关监理招标；（6）组织主体工程施工招标的准备工作等。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]