[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127837,793,1,"单选题","水利工程具备开工条件后，（ ）将开工情况的书面报告报项目主管单位和上一级主管单位备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目法人",true,{"key":16,"text":17,"correct":18},"B","监理单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","质量监督机构","本题考查的是水利工程建设实施阶段的工作内容。水利工程具备开工条件后，主体工程方可开工建设。项目法人或建设单位应当自工程开工之日起15个工作日内，将开工情况的书面报告报项目主管单位和上一级主管单位备案。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]