[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127792":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127792,793,1,"单选题","平板闸门安装顺序的最后一步是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按照预埋件调配止水和支承导向部件",false,{"key":16,"text":17,"correct":14},"B","安装闸门拉杆",{"key":19,"text":20,"correct":14},"C","在门槽内试验闸门的提升和关闭",{"key":22,"text":23,"correct":24},"D","将闸门处于试验水头并投入试运行",true,"本题考查的是金属结构安装的基本要求。平板闸门安装的顺序是：闸门放到门底坎；按照预埋件调配止水和支承导向部件；安装闸门拉杆；在门槽内试验闸门的提升和关闭；将闸门处于试验水头并投入试运行。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]