[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127758,793,1,"单选题","固结灌浆施工程序依次是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻孔:压水试验:灌浆:封孔和质量检查",true,{"key":16,"text":17,"correct":18},"B","钻孔:压水试验:灌浆:质量检查和封孔",false,{"key":20,"text":21,"correct":18},"C","钻孔:灌浆:压水试验:封孔和质量检查",{"key":23,"text":24,"correct":18},"D","钻孔:灌浆:压水试验:质量检查和封孔","本题考查的是灌浆工艺和技术要求。固结灌浆施工程序依次是钻孔、压水试验、灌浆、封孔和质量检查等。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]