[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127707,793,1,"单选题","某水闸底板厚1.6m，其钢筋示意图如下。其中编号为()钢筋的费用不单独计列，应摊入有效重量的工程单价中。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①",false,{"key":16,"text":17,"correct":14},"B","②",{"key":19,"text":20,"correct":14},"C","③",{"key":22,"text":23,"correct":24},"D","④",true,"钢筋按施工图纸所示钢筋强度等级、直径和长度计算的有效重量以吨为单位计量，由发包人按《工程量清单》相应项B有效工程量的每吨工程单价支付。施丁架立筋、搭接、套茼连接、加工及安装过程中操作损耗等所需费用，均包含在《工程量清单》相应项目有效丁程量的每吨工程单价中.不另行支付。4为架立筋",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]