[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127696,793,1,"单选题","平板钢闸门安装中，闸门压向主轨时，止水与预埋件之间应保持()mm的富裕度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1～3",false,{"key":16,"text":17,"correct":18},"B","3～5",true,{"key":20,"text":21,"correct":14},"C","5～7",{"key":23,"text":24,"correct":14},"D","7～9","【考点】水利水电工程金属结构分类及安装要求。 平板闸门包括直升式和升卧式两种形式。平板闸门的门叶由承重结构[包括：面板、梁系、竖向连接系或隔板、门背（纵向）连接系和支承边梁等]、行走支承、止水装置和吊耳等组成。安装前，检查闸门和支承导引部件的几何尺寸，消除出现的损伤，清理闸门的泥土和锈迹，润滑支承导向部件，建立记录。闸门的检查应在水平台架上进行。平板闸门安装的顺序是：闸门放到门底坎；按照预埋件调配止水和支承导向部件；安装闸门拉杆；在门槽内试验闸门的提升和关闭；将闸门处于试验水头并投入试运行。安装行走部件时，应使其所有滚轮（或滑块）都同时紧贴主轨；闸门压向主轨时，止水与预埋件之间应保持3～5mm的富裕度。故本题应选B。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]