[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127683,793,1,"单选题","（2020年真题）下列文件中，不属于水利水电工程注册建造师施工管理签章文件的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工技术方案报审表",false,{"key":16,"text":17,"correct":14},"B","联合测量通知单",{"key":19,"text":20,"correct":21},"C","监理通知签收单",true,{"key":23,"text":24,"correct":14},"D","合同项目开工令","P369-372 水利水电工程注册建造师施工管理签章文件为下表，其中不包括监理通知签收单。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]