[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127648,793,1,"单选题","根据《水利工程建设项目施工监理规范》（SL288—2003），监理单位跟踪监测土方式样的数量应不少于承包人检测数量的（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":14},"B","5%",{"key":19,"text":20,"correct":14},"C","7%",{"key":22,"text":23,"correct":24},"D","10%",true,"监理机构可采用跟踪检测、平行检测方法对承包人的检验结果进行复核。平行检测的检测数量，混凝土试样不应少于承包人检测数量的3%;重要部位每种强度等级的混凝土最少取样1组；土方试样不应少于承包人检测数量的5%;重要部位至少取样3组；跟踪检测的检测数量，混凝土试样不应少于承包人检测数量的7%，土方试样不应少于承包人检测数量的10%。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]