[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127645,793,1,"单选题","（2018年）根据《水电工程验收管理力法》(国能新能[2015]426号)，工程蓄水验收的申请，应由项目法人在计划下闸蓄水前（），向工程所在地省级人民政府能源主管部门报送。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1个月",false,{"key":16,"text":17,"correct":14},"B","3个月",{"key":19,"text":20,"correct":21},"C","6个月",true,{"key":23,"text":24,"correct":14},"D","12个月","项目法人应根据工程进度安排，在计划下闸蓄水前6个月，向工程所在地省级人民政府能源主管部门报送工程蓄水验收申请，并抄送验收主持单位。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]