[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127640,793,1,"单选题","根据《水利工程建设项目档案管理规定》，水利工程竣工图的竣工图确认章应由()加盖。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":18},"B","监理单位",true,{"key":20,"text":21,"correct":14},"C","项目法人",{"key":23,"text":24,"correct":14},"D","档案业务主管部门","③凡涉及结构形式、工艺、平面布置等重大改变，或图面变更超过1\u002F3的，应重新绘制竣工图可不再加盖竣工图章）。重绘图应按原图编号，并在说明栏内注明变更依据，在图标栏内注明竣工阶段和绘制竣工图的时间、单位、责任人。监理单位应在图标上方加盖并签署竣工图确认章。可见B选项正确",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]