[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1127639,793,1,"单选题","根据《小型水电站建设工程验收规程》（SL168-2012）下列验收中，不属于小型水电站工程法人验收的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部工程验收",false,{"key":16,"text":17,"correct":18},"B","分项工程验收",true,{"key":20,"text":21,"correct":14},"C","单位工程验收",{"key":23,"text":24,"correct":14},"D","合同工程完工验收","法人验收应包括分部工程验收、单位工程验收、水电站（泵站）中间机组启动验收、合同工程完工验收等；",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]