[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1127638,793,1,"单选题","根据《水利水电建设工程验收规程》SL223―2008，水利工程竣工验收应在工程建设项目全部完成并满足一定运行条件后()年内进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","5","水利工程竣工验收，根据《水利水电建设工程验收规程》SL223—2008,竣工验收应在工程建设项目全部完成并满足一定运行条件后1年内进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]