[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127635,793,1,"单选题","根据《小型水电站建设工程验收规程》SL168-96，小水电工程试生产期限最短为()个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","12","试生产期限，机组启动试运行后确认可以安全试运行，由启动验收委员会提出机组启动验收鉴定书。提出机组启动验收鉴定书后，应办理机组交接手续进行试生产运行，试生产期限为6个月（经过一个汛期）至12个月。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]