[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1127628,793,1,"单选题","某水库工程验收工作中，属于政府验收的是()验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部工程",false,{"key":16,"text":17,"correct":14},"B","单位工程",{"key":19,"text":20,"correct":14},"C","合同工程完工",{"key":22,"text":23,"correct":24},"D","下闸蓄水",true,"根据《水利水电建设工程验收规程》SL223—2008,水利水电建设工程验收按验收主持单位可分为法人验收和政府验收。法人验收应包括分部工程验收、单位工程验收、水电站（泵站）中间机组启动验收、合同工程完工验收等；政府验收应包括阶段验收、专项验收、竣工验收等。验收主持单位可根据工程建设需要增设验收的类别和具体要求。P250原文是(1)阶段验收应包括枢纽工程导（截）流验收、水库下闸蓄水验收、引（调）排水工程通水验收、水电站（泵站）首（末）台机组启动验收、部分工程投入使用验收以及竣工验收主持单位根据工程建设需要增加的其他验收。故下闸蓄水验收为阶段性验收，属于政府验收，答案为D",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]