[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1127619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1127619,793,1,"单选题","（2019年）根据《水利部关于修订印发水利建设质量工作考核办法的通知》（水建管[2018]102号），对省级水行政主管部门考核时,其中项目考核得分占考核总分的（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","30%",{"key":19,"text":20,"correct":21},"C","40%",true,{"key":23,"text":24,"correct":14},"D","50%","根据《水利部关于修订印发水利建设质量工作考核办法的通知》(水建管[2018]102号)，每年对省级水行政主管部 门进行水利建设质量工作考核。每年7月1日至次年6月30日为一个考核年度。考核采用评分和排名相结合的综合评定法，满分为100分，其中总体考核得分占考核总分的60%，项目考核得分占考核总分的40%。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]